Helium One (AIM: HE1), the primary helium explorer in Tanzania, is pleased to provide the following update on its Rukwa Project.
Destacados
· Itumbula West-1 extended well test ("EWT") remains on track for early Q3 2024;
· Environmental and Social Impact Assessment ("ESIA") study commenced as part of the Mining Licence conversion process;
· Appointment of production facilities management company to commence a design study for a helium production plant at Rukwa;
· The Company is continuing to work with the Tanzanian Government and the Mining Commission to move the Rukwa Project towards commercialisation; and
· Expansion and strengthening of Company's technical team in order to progress the Phase III work programme
Lorna Blaisse, directora ejecutiva, comentó:
"We are very pleased to be advancing into this next stage of the Rukwa Project - Phase III. Whilst we are preparing for the next operational phase, which includes the EWT at Itumbula West-1, we are growing the team to deliver the large amount of work that is continuing in the background and that will enable us to progress the project as quickly as possible.
The ESIA will form part of the feasibility study that will be submitted to the Mining Commission in order to convert the existing Prospecting Licences ("PL") to Mining Licences ("ML"). The newly recruited team has already commenced this workstream, and we are grateful for the continued support from the Government and the Mining Commission in Tanzania, as we move the project forward in the next phase of its development towards commercialisation.
Esperamos proporcionar más actualizaciones a su debido tiempo".
ESIA study
The ESIA is part of the feasibility study which is central to the licence conversion process that is required by the Mining Commission in Tanzania. As the ESIA is expected to take approximately six months to complete, the Company has commenced the work now so that the results can align with the EWT and, upon completion of both, will then allow the Company to complete the feasibility study ahead of submitting the ML conversion application.
La Compañía ha designado MTL Consulting Ltd ("MTL"), a Tanzanian company, for the ESIA and will continue to work with them to compile and deliver a detailed report to the National Environmental Management Council within the necessary timeframe. As well as the ESIA study, the Company will also undertake more detailed subsurface work and plans to establish contingent resource estimates which will form part of the Feasibility Study.
Production facility study
The Company has also commenced above-ground engineering studies and, following a detailed review of several companies, has now selected one to produce a preliminary design for a production system that will be suited to the flow rates and gas composition within the Rukwa Basin.
This study has commenced with several processing facility options already being reviewed. These will include a smaller, lower rate pilot plant that would allow for early production as well as larger, modular systems that can be scaled-up. The design work will include helium liquefaction, storage and transportation with the aim of providing a well head to off-taker processing system. This would enable the Company to streamline all downstream and mid-stream activities.
EWT and future drilling update
The Company has commenced ordering the long lead items for the Itumbula West-1 EWT and is currently reviewing the merits of re-entering and deepening the Tai-3 well or pursuing a new exploration/appraisal well. Amongst other considerations, this decision will be made on the back of delivery times for the necessary equipment and the availability of third-party service companies.
Para obtener más información, visite el sitio web de la empresa: www.helio-uno.com
Contacto
Helio uno global ltd Lorna Blaisse, directora general | +44 20 7920 3150 |
| |
Liberum Capital Limited (Asesor Designado y Broker) Scott Mathieson Ed Tomas Nikhil Varghese | +44 20 3100 2000 |
| |
Tavistock (Relaciones públicas financieras) nick elwes Tara Vivian - Neal | +44 20 7920 3150
|
Notas a los editores
Helium One Global, the AIM-listed Tanzanian explorer, holds prospecting licences across three distinct project areas, with the potential to become a strategic player in resolving a supply-constrained helium market.
The Rukwa, Balangida, and Eyasi projects are located within rift basins on the margin of the Tanzanian Craton in the north and southwest of the country. The assets lie near surface seeps with helium concentrations ranging up to 10.6% helium by volume. All Helium One's licences are held on a 100% equity basis.
El proyecto insignia de la compañía Rukwa se encuentra dentro de la cuenca del Rift de Rukwa que cubre 1,900 km.2 in south-west Tanzania. This project is considered to be entering an appraisal stage following the success of the 2023/24 drilling campaign, which has proved an established helium system where the Itumbula West-1 exploration well successfully flowed 4.7% helium to surface in Q1 2024. Additional follow on leads and prospects are defined by a subsurface database including multispectral satellite spectroscopy, airborne gravity gradiometry, 2D seismic data, and QEMSCAN analysis.
Helium One cotiza en el mercado AIM de la Bolsa de Valores de Londres con el símbolo de cotización HE1 y en el OTCQB de los Estados Unidos con el símbolo de cotización HLOGF.
RNS puede usar su dirección IP para confirmar el cumplimiento de los términos y condiciones, para analizar cómo interactúa con la información contenida en esta comunicación y para compartir dicho análisis de forma anónima con otros como parte de nuestros servicios comerciales. Para obtener más información sobre cómo RNS y la Bolsa de Valores de Londres utilizan los datos personales que nos proporciona, consulte nuestra Política de privacidad.